Kadri Residency B Wing, Ghatkopar West

by Mohamed Yaqub Abbasali Khan · Ghatkopar West, Mumbai 400086 · Map

Launched
Feb 20252 yrs 10 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
90%Mid-construction
Booked
–
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
24
Total units
25
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services40%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 85%Oct 2026: Concrete structure (RCC) 90%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 40%Excavation 100%Concrete structure (RCC) 90%Final finishes 40%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%40%–
100%85%0%–
100%10%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400086

Projects with 10–50 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400086
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths2 yrs 9 mths
Possession date extendedNo1 of 3
Possession date (MahaRERA)Dec 2027Oct 2027
Concrete structure (RCC)90%12%
Units booked–45%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Kadri Residency B Wing by Mohamed Yaqub Abbasali Khan is a 25-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in February 2025 with possession due in December 2027. The concrete structure (RCC) is 90% complete.

Read full summary

Kadri Residency B Wing is a BMC-sanctioned project by Mohamed Yaqub Abbasali Khan in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800079094. It was launched in February 2025. It has 25 units in 1 building, with 1 RK and 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes 40% complete.

Since the July 2026 update, the reported concrete structure (RCC) has gone from 85% to 90%.