Aadhya, Kandivali West
by Gagangiri Construction · Kandivali West, Mumbai 400067 · Map
- Launched
- Feb 20254 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 90%Mid-construction
- Booked (free sale)
- 66 of 8479% · 18 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale66 booked out of 84 units
Rehab18 units for existing members
Total 102 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 36
- 2 BHK
- 43
- 3 BHK
- 20
- Other units
- 3
- Total units
- 102
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 84
- Rehab units
- 18
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 30% | 66 | |
| 100% | 40% | 0% | 33 | |
| 100% | 15% | 0% | 22 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 10 mths | 2 yrs 10 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2029 | Dec 2027 |
| Concrete structure (RCC) | 90% | 26% |
| Units booked (free sale) | 79% | 78% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Sukan Co-Operative Housing Society Limited, Kandivali West
- Vraj Mangalam, Kandivali West
- Pratima Heights, Kandivali West
- Ambit Primoris, Kandivali West
- Navrang Laxmi, Kandivali West
- Redevelopment Of Rajesh Mandir Chsl, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sukan Co-Operative Housing Society Limited | February 2025 | June 2027 | 10% | 17 units booked out of 29 units for sale |
| Vraj Mangalam | February 2025 | October 2028 | 100% | 18 units booked out of 23 units for sale |
| Pratima Heights | February 2025 | December 2027 | 0% | – |
| Ambit Primoris | January 2025 | December 2027 | 0% | 164 units booked out of total 183 units |
| Navrang Laxmi | March 2025 | December 2027 | 43% | 33 units booked out of 41 units for sale |
| Redevelopment Of Rajesh Mandir Chsl | March 2025 | July 2028 | 80% | 18 units booked out of 26 units for sale |
About this project
Aadhya by Gagangiri Construction is a 102-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in February 2025 with possession due in December 2029. 66 units booked out of 84 units for sale. The concrete structure (RCC) is 90% complete.
Read full summary
Aadhya is a MHADA-sanctioned project by Gagangiri Construction in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800079135. It was launched in February 2025. It has 102 units in 1 building: 99 homes (1, 2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 102 units, 84 are for sale and 18 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes 30% complete.
66 units booked out of 84 units for sale (79%). Since the July 2026 update, 33 more units have been booked and the reported concrete structure (RCC) has gone from 40% to 90%.