Navrang Laxmi, Kandivali West
by Oxford Downtown Realty LLP · Kandivali West, Mumbai 400067 · Map
- Launched
- Mar 20252 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 43%Mid-construction
- Booked (free sale)
- 33 of 4180% · 28 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale33 booked out of 41 units
Rehab28 units for existing members
Total 69 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 2
- 2 BHK
- 54
- 3 BHK
- 8
- 4 BHK
- 1
- Other units
- 4
- Total units
- 69
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 41
- Rehab units
- 28
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 43% | 0% | 33 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 3 yrs 1 mth |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Mar 2028 |
| Concrete structure (RCC) | 43% | 77% |
| Units booked (free sale) | 80% | 69% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Redevelopment Of Rajesh Mandir Chsl, Kandivali West
- Rashmi Delight, Kandivali West
- Sukan Co-Operative Housing Society Limited, Kandivali West
- Vraj Mangalam, Kandivali West
- Pratima Heights, Kandivali West
- Aadhya, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Redevelopment Of Rajesh Mandir Chsl | March 2025 | July 2028 | 80% | 18 units booked out of 26 units for sale |
| Rashmi Delight | March 2025 | December 2026 | 74% | 14 units booked out of 26 units for sale |
| Sukan Co-Operative Housing Society Limited | February 2025 | June 2027 | 10% | 17 units booked out of 29 units for sale |
| Vraj Mangalam | February 2025 | October 2028 | 100% | 18 units booked out of 23 units for sale |
| Pratima Heights | February 2025 | December 2027 | 0% | – |
| Aadhya | February 2025 | December 2029 | 90% | 66 units booked out of 84 units for sale |
About this project
Navrang Laxmi by Oxford Downtown Realty LLP is a 69-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in March 2025 with possession due in December 2027. 33 units booked out of 41 units for sale. The concrete structure (RCC) is 43% complete.
Read full summary
Navrang Laxmi is a MHADA-sanctioned project by Oxford Downtown Realty LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800079415. It was launched in March 2025. It has 69 units in 1 building: 65 homes (1, 2, 3 and 4 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 69 units, 41 are for sale and 28 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 43% complete, final finishes not started.
33 units booked out of 41 units for sale (80%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 43%.