Axiom Gurubhakti, Mulund East

by Axiom Refab Construction (India) Pvt Ltd · Mulund East, Mumbai 400081 · Map

Launched
Feb 20253 yrs 8 mths promised
Possession (MahaRERA)
Oct 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
20 of 3262%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale20 booked out of 32 units

Land-owner share23 units, not for sale

Total 55 units. Land-owner units are not for sale.

Project facts

1 BHK
1
2 BHK
46
3 BHK
1
Other units
7
Total units
55
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
32
Land-owner share (not for sale)
23

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services25%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 8%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 10%Oct 2026: Final finishes 25%Excavation 100%Concrete structure (RCC) 100%Final finishes 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%25%20
100%100%10%12
100%8%0%4

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400081

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400081
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths3 yrs 4 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Oct 2028Jun 2028
Concrete structure (RCC)100%96%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Axiom Gurubhakti by Axiom Refab Construction (India) Pvt Ltd is a 55-unit BMC-sanctioned project in Mulund East, Mumbai 400081, launched in February 2025 with possession due in October 2028. 20 units booked out of 32 units for sale. The concrete structure (RCC) is complete.

Read full summary

Axiom Gurubhakti is a BMC-sanctioned project by Axiom Refab Construction (India) Pvt Ltd in Mulund East, Mumbai 400081, registered with MahaRERA as P51800079169. It was launched in February 2025. It has 55 units in 1 building: 48 homes (1, 2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 55 units, 32 are for sale and 23 are the land-owner's share, not for sale.

Its registered possession date is October 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 25% complete.

20 units booked out of 32 units for sale (62%). Since the July 2026 update, 8 more units have been booked.