Satre Elite, Mulund East

by Ramchandra Vitthal Satre · Mulund East, Mumbai 400081 · Map

Launched
Feb 20253 yrs 4 mths promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
96%Mid-construction
Booked (free sale)
13 of 3438% · 12 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale13 booked out of 34 units

Rehab12 units for existing members

Total 46 units. Rehab units are not for sale.

Project facts

1 BHK
25
2 BHK
16
Other units
5
Total units
46
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
34
Rehab units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)96%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 10%Jul 2026: Excavation 10%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 96%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 96%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%96%0%13
10%0%0%20
10%0%0%20

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400081

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400081
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths3 yrs 8 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Jun 2028Oct 2028
Concrete structure (RCC)96%100%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Satre Elite by Ramchandra Vitthal Satre is a 46-unit SRA-sanctioned project in Mulund East, Mumbai 400081, launched in February 2025 with possession due in June 2028. 13 units booked out of 34 units for sale. The concrete structure (RCC) is 96% complete.

Read full summary

Satre Elite is an SRA-sanctioned project by Ramchandra Vitthal Satre in Mulund East, Mumbai 400081, registered with MahaRERA as P51800079273. It was launched in February 2025. It has 46 units in 1 building: 41 homes (1 and 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 46 units, 34 are for sale and 12 are rehab units for existing members.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 96% complete, final finishes not started.

13 units booked out of 34 units for sale (38%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 96%.