Skip to main content

Rishab Om Brij Kutir, Malad East

by Rishab Infra · Malad East, Mumbai 400097 · Map

Launched
Feb 20252 yrs 10 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
20 of 2580% · 21 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale20 booked out of 25 units

Rehab21 units for existing members

Total 46 units. Rehab units are not for sale.

Project facts

1 RK
5
1 BHK
25
2 BHK
12
Other units
4
Total units
46
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
25
Rehab units
21

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 40%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%20
100%60%0%17
100%40%0%13

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400097

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths3 yrs 8 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2027Dec 2028
Concrete structure (RCC)100%35%
Units booked (free sale)80%40%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Rishab Om Brij Kutir by Rishab Infra is a 46-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in February 2025 with possession due in December 2027. 20 units booked out of 25 units for sale. The concrete structure (RCC) is complete.

Read full summary

Rishab Om Brij Kutir is a BMC-sanctioned project by Rishab Infra in Malad East, Mumbai 400097, registered with MahaRERA as P51800079288. It was launched in February 2025. It has 46 units in 1 building: 42 homes (1 RK, 1 BHK and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 46 units, 25 are for sale and 21 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

20 units booked out of 25 units for sale (80%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 60% to 100%.