Sarjivan Bldg No 2 Coop Hsg soc Limited, Malad East
by Sarjivan Bldg No 2 Coop Hsg Soc Limited · Malad East, Mumbai 400097 · Map
- Launched
- Apr 20253 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 60%Mid-construction
- Booked (free sale)
- 12 of 3238% · 31 rehab units
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale12 booked out of 32 units
Rehab31 units for existing members
Total 63 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 12
- 2 BHK
- 25
- 3 BHK
- 26
- Total units
- 63
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 32
- Rehab units
- 31
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 95% | 60% | 0% | 12 | |
| 95% | 20% | 0% | 7 | |
| 10% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400097
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 8 mths | 3 yrs |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Dec 2028 | Jun 2028 |
| Concrete structure (RCC) | 60% | 36% |
| Units booked (free sale) | 38% | 69% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Rishab Om Brij Kutir, Malad East
- Royal Regency Heights, Malad East
- Pramod Apartment Chs Ltd, Malad East
- Vastunemi Good Luck Apartment, Malad East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rishab Om Brij Kutir | February 2025 | December 2027 | 100% | 20 units booked out of 25 units for sale |
| Royal Regency Heights | June 2025 | December 2028 | 39% | 80 units booked out of total 136 units |
| Pramod Apartment Chs Ltd | December 2024 | October 2027 | 0% | 23 units booked out of 25 units for sale |
| Vastunemi Good Luck Apartment | September 2025 | December 2028 | 32% | 6 units booked out of 20 units for sale |
About this project
Sarjivan Bldg No 2 Coop Hsg soc Limited by Sarjivan Bldg No 2 Coop Hsg Soc Limited is a 63-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in April 2025 with possession due in December 2028. 12 units booked out of 32 units for sale. The concrete structure (RCC) is 60% complete.
Read full summary
Sarjivan Bldg No 2 Coop Hsg soc Limited is a BMC-sanctioned project by Sarjivan Bldg No 2 Coop Hsg Soc Limited in Malad East, Mumbai 400097, registered with MahaRERA as P51800079945. It was launched in April 2025. It has 63 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 63 units, 32 are for sale and 31 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation 95% complete, structure (RCC) 60% complete, final finishes not started.
12 units booked out of 32 units for sale (38%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 20% to 60%.