Charkop 1 Ramtirth Chsl, Kandivali West

by Shivraj Realtech LLP · Kandivali West, Mumbai 400067 · Map

Launched
Mar 20252 yrs 9 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 60% · 2 rehab units
Buildings
20.3 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 6 units

Rehab2 units for existing members

Total 8 units. Rehab units are not for sale.

Project facts

1 BHK
6
2 BHK
2
Total units
8
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
2
Free-sale units
6
Rehab units
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%0
0%0%0%0
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400067

Projects with up to 20 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 9 mths3 yrs 8 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2027Sep 2029
Concrete structure (RCC)0%0%
MahaRERA complaints (filed by or against the builder)20

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Charkop 1 Ramtirth Chsl by Shivraj Realtech LLP is an 8-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in March 2025 with possession due in December 2027. 0 units booked out of 6 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Charkop 1 Ramtirth Chsl is a MHADA-sanctioned project by Shivraj Realtech LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800079530. It was launched in March 2025. It has 8 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 8 units, 6 are for sale and 2 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

0 units booked out of 6 units for sale (0%).