West Center Meridian Court, Kandivali West

by Vijaykamal Properties Pvt Ltd · Kandivali West, Mumbai 400067 · Map

Launched
Sep 20255 yrs 3 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
0%Early stage
Booked
18 of 3453% · 17 in Jul 2026
Buildings
111.8 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
13
2 BHK
2
Other units
19
Total units
34
Buildings
1
Land
11.8 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation6%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 6%Oct 2026: Excavation 6%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 6%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
6%0%0%18
6%0%0%17
0%0%0%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400067

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 3 mths2 yrs 11 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2030Mar 2028
Concrete structure (RCC)0%8%
Units booked53%0%
MahaRERA complaints (filed by or against the builder)10

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

West Center Meridian Court by Vijaykamal Properties Pvt Ltd is a 34-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in September 2025 with possession due in December 2030. 18 units booked out of total 34 units. Work on the concrete structure (RCC) has not started.

Read full summary

West Center Meridian Court is an SRA-sanctioned project by Vijaykamal Properties Pvt Ltd in Kandivali West, Mumbai 400067, registered with MahaRERA as PM1181012500995. It was launched in September 2025. It has 34 units in 1 building: 15 homes (1 and 2 BHK) and 19 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation 6% complete, structure (RCC) not started, final finishes not started.

18 units booked out of total 34 units (53%). Since the July 2026 update, 1 more unit has been booked.