Skip to main content

Dream Skyview, Mulund West

by Dream Constructions · Mulund West, Mumbai 400080 · Map

Launched
Apr 20253 yrs 8 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
5 of 559% · 46 rehab units
Buildings
10.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 55 units

Rehab46 units for existing members

Total 101 units. Rehab units are not for sale.

Project facts

1 BHK
7
2 BHK
90
3 BHK
4
Total units
101
Buildings
1
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
55
Rehab units
46

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%5
100%0%0%5
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths3 yrs 7 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028Dec 2028
Concrete structure (RCC)0%0%
Units booked (free sale)9%26%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Dream Skyview by Dream Constructions is a 101-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in April 2025 with possession due in December 2028. 5 units booked out of 55 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Dream Skyview is a BMC-sanctioned project by Dream Constructions in Mulund West, Mumbai 400080, registered with MahaRERA as P51800080063. It was launched in April 2025. It has 101 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 101 units, 55 are for sale and 46 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

5 units booked out of 55 units for sale (9%).