Axiom Vriksh, Mulund West
by Axiom Refab Construction (India) Pvt Ltd · Mulund West, Mumbai 400080 · Map
- Launched
- May 20254 yrs 6 mths promised
- Possession (MahaRERA)
- Nov 2029Not extended
- Concrete structure
- 50%Mid-construction
- Booked (free sale)
- 6 of 4214%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale6 booked out of 42 units
Land-owner share16 units, not for sale
Total 58 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 2
- 2 BHK
- 50
- Other units
- 6
- Total units
- 58
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 42
- Land-owner share (not for sale)
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 50% | 0% | 6 | |
| 100% | 15% | 0% | 2 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400080
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 6 mths | 3 yrs 4 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Nov 2029 | Sep 2028 |
| Concrete structure (RCC) | 50% | 0% |
| Units booked (free sale) | 14% | 23% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Vighnaharta Apartments, Mulund West
- Aum Laxmi Kusum, Mulund West
- Omkar Sejal, Mulund West
- Ambe Mahal Centre One, Mulund West
- Dream Skyview, Mulund West
- Stuti, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vighnaharta Apartments | May 2025 | July 2028 | 0% | – |
| Aum Laxmi Kusum | April 2025 | December 2028 | 0% | – |
| Omkar Sejal | June 2025 | June 2028 | 25% | 0 units booked out of 17 units for sale |
| Ambe Mahal Centre One | June 2025 | December 2028 | 0% | 111 units booked out of total 121 units |
| Dream Skyview | April 2025 | December 2028 | 0% | 5 units booked out of 55 units for sale |
| Stuti | March 2025 | December 2027 | 0% | 15 units booked out of 40 units for sale |
About this project
Axiom Vriksh by Axiom Refab Construction (India) Pvt Ltd is a 58-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in May 2025 with possession due in November 2029. 6 units booked out of 42 units for sale. The concrete structure (RCC) is 50% complete.
Read full summary
Axiom Vriksh is an SRA-sanctioned project by Axiom Refab Construction (India) Pvt Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as P51800080270. It was launched in May 2025. It has 58 units in 1 building: 52 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 58 units, 42 are for sale and 16 are the land-owner's share, not for sale.
Its registered possession date is November 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.
6 units booked out of 42 units for sale (14%). Since the July 2026 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 15% to 50%.