Meera Upvan Co-Operative Housing Society Limited, Borivali East
by Yogiraj Builders And Developers · Borivali East, Mumbai 400066 · Map
- Launched
- Apr 20252 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 95%Mid-construction
- Booked (free sale)
- 0 of 200% · 18 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 20 units
Rehab18 units for existing members
Total 38 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 12
- 2 BHK
- 11
- Other units
- 15
- Total units
- 38
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 20
- Rehab units
- 18
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 0% | 0 | |
| 100% | 95% | 0% | 0 | |
| 100% | 18% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400066
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 8 mths | 2 yrs 8 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Nov 2027 |
| Concrete structure (RCC) | 95% | 80% |
| Units booked (free sale) | 0% | 32% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Diwali Darshan, Borivali East
- Amaira Pallazo, Borivali East
- Swanand Co-Operative Housing Society Limited, Borivali East
- Sadguru Trimurti, Borivali East
- Shreenath Regency, Borivali East
- Parshuram Heights, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Diwali Darshan | April 2025 | February 2027 | 81% | 2 units booked out of 27 units for sale |
| Amaira Pallazo | May 2025 | November 2030 | 100% | 50 units booked out of 162 units for sale |
| Swanand Co-Operative Housing Society Limited | March 2025 | December 2027 | 70% | 11 units booked out of 28 units for sale |
| Sadguru Trimurti | December 2024 | August 2027 | 95% | 15 units booked out of total 28 units |
| Shreenath Regency | August 2025 | October 2027 | 70% | 1 unit booked out of 3 units for sale |
| Parshuram Heights | August 2025 | September 2028 | 80% | 1 unit booked out of 32 units for sale |
About this project
Meera Upvan Co-Operative Housing Society Limited by Yogiraj Builders And Developers is a 38-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in April 2025 with possession due in December 2027. 0 units booked out of 20 units for sale. The concrete structure (RCC) is 95% complete.
Read full summary
Meera Upvan Co-Operative Housing Society Limited is a BMC-sanctioned project by Yogiraj Builders And Developers in Borivali East, Mumbai 400066, registered with MahaRERA as P51800080078. It was launched in April 2025. It has 38 units in 1 building: 23 homes (1 and 2 BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 38 units, 20 are for sale and 18 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 95% complete, final finishes not started.
0 units booked out of 20 units for sale (0%).