Diwali Darshan, Borivali East
by Omkar Engineers And Contractors · Borivali East, Mumbai 400066 · Map
- Launched
- Apr 20259 mths originally promised
- Possession (MahaRERA)
- Feb 2027Extended by 1 yr 1 mth
- Concrete structure
- 81%Mid-construction
- Booked (free sale)
- 2 of 277% · 44 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale2 booked out of 27 units
Rehab44 units for existing members
Total 71 units. Rehab units are not for sale.
Project facts
- 1 RK
- 5
- 1 BHK
- 19
- 2 BHK
- 14
- 3 BHK
- 1
- Other units
- 32
- Total units
- 71
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 27
- Rehab units
- 44
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 81% | 0% | 2 | |
| 100% | 81% | 0% | 2 | |
| 80% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400066
Projects with 10–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 9 mths | 2 yrs 8 mths |
| Possession date extended | By 1 yr 1 mth | 0 of 6 |
| Possession date (MahaRERA) | Feb 2027 | Dec 2027 |
| Concrete structure (RCC) | 81% | 82% |
| Units booked (free sale) | 7% | 6% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 6 projects
- Meera Upvan Co-Operative Housing Society Limited, Borivali East
- Amaira Pallazo, Borivali East
- Swanand Co-Operative Housing Society Limited, Borivali East
- Devikunj Co-Operative Housing Society Limited, Borivali East
- Rajendra Nagar Omsai Co-Operative Housing Society Limited, Borivali East
- Sambhav Darshan Purshottam Park CO-OPERATIVE HOUSING SOCIETY LTD, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Meera Upvan Co-Operative Housing Society Limited | April 2025 | December 2027 | 95% | 0 units booked out of 20 units for sale |
| Amaira Pallazo | May 2025 | November 2030 | 100% | 50 units booked out of 162 units for sale |
| Swanand Co-Operative Housing Society Limited | March 2025 | December 2027 | 70% | 11 units booked out of 28 units for sale |
| Devikunj Co-Operative Housing Society Limited | May 2025 | December 2027 | 62% | 0 units booked out of 13 units for sale |
| Rajendra Nagar Omsai Co-Operative Housing Society Limited | January 2025 | December 2027 | 100% | 1 unit booked out of 22 units for sale |
| Sambhav Darshan Purshottam Park CO-OPERATIVE HOUSING SOCIETY LTD | July 2025 | December 2027 | 18% | 2 units booked out of 27 units for sale |
About this project
Diwali Darshan by Omkar Engineers And Contractors is a 71-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in April 2025 with possession due in February 2027. 2 units booked out of 27 units for sale. The concrete structure (RCC) is 81% complete.
Read full summary
Diwali Darshan is a BMC-sanctioned project by Omkar Engineers And Contractors in Borivali East, Mumbai 400066, registered with MahaRERA as P51800080143. It was launched in April 2025. It has 71 units in 1 building: 39 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 32 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 71 units, 27 are for sale and 44 are rehab units for existing members.
Its registered possession date is February 2027, extended by 1 year 1 month from the original January 2026. Construction: excavation complete, structure (RCC) 81% complete, final finishes not started.
2 units booked out of 27 units for sale (7%).