Crystal Vista, Santacruz East
by M/s. Crystal Developers · Santacruz East, Mumbai 400055 · Map
- Launched
- Apr 20252 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 30%Mid-construction
- Booked (free sale)
- 9 of 4819% · 31 rehab units
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale9 booked out of 48 units
Rehab31 units for existing members
Land-owner share13 units, not for sale
Total 92 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 79
- 2 BHK
- 7
- Other units
- 6
- Total units
- 92
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 48
- Rehab units
- 31
- Land-owner share (not for sale)
- 13
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 30% | 0% | 9 | |
| 100% | 60% | 0% | – | |
| 100% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400055
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 8 mths | 2 yrs 1 mth |
| Possession date extended | No | 2 of 3 |
| Possession date (MahaRERA) | Dec 2027 | Jun 2027 |
| Concrete structure (RCC) | 30% | 70% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Space Grandeur, Santacruz East
- Royal Mansion, Santacruz East
- Miraya Residency, Santacruz East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Space Grandeur | November 2024 | June 2027 | 70% | 15 units booked out of 27 units for sale |
| Royal Mansion | November 2024 | December 2028 | 0% | – |
| Miraya Residency | October 2024 | Dec 2026 – Dec 2028 | 73% | 9 units booked out of 41 units for sale |
About this project
Crystal Vista by M/s. Crystal Developers is a 92-unit BMC-sanctioned project in Santacruz East, Mumbai 400055, launched in April 2025 with possession due in December 2027. 9 units booked out of 48 units for sale. The concrete structure (RCC) is 30% complete.
Read full summary
Crystal Vista is a BMC-sanctioned project by M/s. Crystal Developers in Santacruz East, Mumbai 400055, registered with MahaRERA as P51800080133. It was launched in April 2025. It has 92 units in 2 buildings: 86 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 92 units, 48 are for sale, 31 are rehab units for existing members and 13 are the land-owner's share, not for sale.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation 50% complete, structure (RCC) 30% complete, final finishes not started.
9 units booked out of 48 units for sale (19%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 60% to 30%.