Miraya Residency, Santacruz East

by S M A Q Infra LLP · Santacruz East, Mumbai 400055 · Map

Launched
Oct 2024First of 2 phases
Possession (MahaRERA)
Dec 2026 – Dec 2028Extended in 1 of 2 phases
Concrete structure
73%Weighted across 2 phases
Booked (free sale)
9 of 4122% · 62 rehab units
Buildings
30.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale9 booked out of 41 units

Rehab62 units for existing members

Total 103 units. Rehab units are not for sale.

Project facts

1 BHK
9
2 BHK
90
Other units
4
Total units
103
Buildings
3
Land
0.5 acres
Phases
2
MahaRERA complaints
0
Free-sale units
41
Rehab units
62

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Miraya Residency
Nearing possession
PM118000240006172100%12%
Miraya Residency C Wing
Early stage
PR1180002600016270%0%
Show updates by phase

Miraya Residency (PM1180002400061)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%9
95%100%0%9
95%100%0%9
90%70%0%0

"–" means MahaRERA shows no figure for that update.

Miraya Residency C Wing (PR1180002600016)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%0%0%0
90%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation97%
Concrete structure (slabs)73%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 94%Oct 2026: Excavation 97%Jul 2026: Concrete structure (RCC) 73%Oct 2026: Concrete structure (RCC) 73%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 97%Concrete structure (RCC) 73%Final finishes 0%

How to read construction stages

Compared with 3 similar projects in PIN 400055

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400055
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 11 mths2 yrs 8 mths
Possession date extendedYes1 of 3
Possession date (MahaRERA)Dec 2026 – Dec 2028Jun 2027
Concrete structure (RCC)73%70%
Units booked (free sale)22%46%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Miraya Residency by S M A Q Infra LLP is a 103-unit BMC-sanctioned project in Santacruz East, Mumbai 400055, registered with MahaRERA in 2 phases, with possession dates from December 2026 to December 2028. 9 units booked out of 41 units for sale. The concrete structure (RCC) is 73% complete.

Read full summary

Miraya Residency is a BMC-sanctioned project by S M A Q Infra LLP in Santacruz East, Mumbai 400055, registered with MahaRERA as 2 phases (PM1180002400061, PR1180002600016). The first phase was launched in October 2024. Together the phases have 103 units in 3 buildings: 99 homes (1 and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA. Of the 103 units, 41 are for sale and 62 are rehab units for existing members.

The phases' registered possession dates run from December 2026 to December 2028; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 73% complete and final finishes 0% complete. Neither phase has its structure complete.

9 units booked out of 41 units for sale (22%).