Rustomjee Crescent, Khar West

by Keyvihar Realtors Private Limited · Khar West, Mumbai 400052 · Map

Launched
May 20254 yrs 7 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
33 of 9933% · 61 rehab units
Buildings
21.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale33 booked out of 99 units

Rehab61 units for existing members

Total 160 units. Rehab units are not for sale.

Project facts

3 BHK
114
4 BHK
40
Other units
6
Total units
160
Buildings
2
Land
1.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
99
Rehab units
61

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 20%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%33
20%0%0%33
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Rustomjee Crescent by Keyvihar Realtors Private Limited (Rustomjee) is a 160-unit SRA-sanctioned project in Khar West, Mumbai 400052, launched in May 2025 with possession due in December 2029. 33 units booked out of 99 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Rustomjee Crescent is an SRA-sanctioned project by Keyvihar Realtors Private Limited in Khar West, Mumbai 400052, registered with MahaRERA as P51800080217. It was launched in May 2025. It has 160 units in 2 buildings: 154 homes (3 and 4 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 160 units, 99 are for sale and 61 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

33 units booked out of 99 units for sale (33%).

Rustomjee's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA38
Total units across these projects3,435
Completed without extending the possession date15
Completed after an extension2
Lapsed5
Under construction16
Possession date extended on the builder's application8
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Rustomjee projects119 (11 of 38 projects)

See all Rustomjee projects →