Skip to main content

Devikunj Co-Operative Housing Society Limited, Borivali East

by Yogiraj Builders And Developers · Borivali East, Mumbai 400066 · Map

Launched
May 20252 yrs 7 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
62%Mid-construction
Booked (free sale)
0 of 130% · 13 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 13 units

Rehab13 units for existing members

Total 26 units. Rehab units are not for sale.

Project facts

1 BHK
8
2 BHK
6
3 BHK
3
Other units
9
Total units
26
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
13
Rehab units
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)62%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 62%Jul 2026: Concrete structure (RCC) 62%Oct 2026: Concrete structure (RCC) 62%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 62%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%62%0%0
100%62%0%0
100%62%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400066

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 7 mths2 yrs 5 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2027Sep 2027
Concrete structure (RCC)62%76%
Units booked (free sale)0%42%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Devikunj Co-Operative Housing Society Limited by Yogiraj Builders And Developers is a 26-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in May 2025 with possession due in December 2027. 0 units booked out of 13 units for sale. The concrete structure (RCC) is 62% complete.

Read full summary

Devikunj Co-Operative Housing Society Limited is a BMC-sanctioned project by Yogiraj Builders And Developers in Borivali East, Mumbai 400066, registered with MahaRERA as P51800080293. It was launched in May 2025. It has 26 units in 1 building: 17 homes (1, 2 and 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 26 units, 13 are for sale and 13 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 62% complete, final finishes not started.

0 units booked out of 13 units for sale (0%).