Skip to main content

Mohanraj Chs Ltd, Kandivali West

by Mohan Enterprises · Kandivali West, Mumbai 400067 · Map

Launched
Mar 20262 yrs promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
16 of 3941% · 32 rehab units
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale16 booked out of 39 units

Rehab32 units for existing members

Total 71 units. Rehab units are not for sale.

Project facts

1 BHK
44
2 BHK
27
Total units
71
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
39
Rehab units
32

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 100%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%16
100%90%0%11

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs4 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Mar 2028Jun 2030
Concrete structure (RCC)100%0%
Units booked (free sale)41%14%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Mohanraj Chs Ltd by Mohan Enterprises is a 71-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in March 2026 with possession due in March 2028. 16 units booked out of 39 units for sale. The concrete structure (RCC) is complete.

Read full summary

Mohanraj Chs Ltd is a BMC-sanctioned project by Mohan Enterprises in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800081101. It was launched in March 2026. It has 71 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 71 units, 39 are for sale and 32 are rehab units for existing members.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

16 units booked out of 39 units for sale (41%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 90% to 100%.