Skip to main content

Maitri Siya Heights, Kandivali West

by Maitri Siya Enterprises · Kandivali West, Mumbai 400067 · Map

Launched
Jan 20264 yrs 11 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
50%Mid-construction
Booked (free sale)
48 of 5489% · 34 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale48 booked out of 54 units

Rehab34 units for existing members

Total 88 units. Rehab units are not for sale.

Project facts

1 BHK
55
2 BHK
22
Other units
11
Total units
88
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
54
Rehab units
34
Reserved units
42

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)50%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 50%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 25%Oct 2026: Concrete structure (RCC) 50%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 50%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%0%48
100%25%0%47
50%0%0%42

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 30–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 11 mths3 yrs 4 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2030Jun 2029
Concrete structure (RCC)50%2%
Units booked (free sale)89%14%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Maitri Siya Heights by Maitri Siya Enterprises is an 88-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in January 2026 with possession due in December 2030. 48 units booked out of 54 units for sale. The concrete structure (RCC) is 50% complete.

Read full summary

Maitri Siya Heights is an SRA-sanctioned project by Maitri Siya Enterprises in Kandivali West, Mumbai 400067, registered with MahaRERA as PM1180002502029. It was launched in January 2026. It has 88 units in 1 building: 77 homes (1 and 2 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 88 units, 54 are for sale and 34 are rehab units for existing members.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.

48 units booked out of 54 units for sale (89%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 25% to 50%.