Shreepati Jewels, Girgaon
by Shreepati Jewels · Girgaon, Mumbai 400004 · Map
- Launched
- Jul 20177 yrs 5 mths originally promised
- Possession (MahaRERA)
- Dec 2032Extended by 8 yrs
- Concrete structure
- 47%Mid-construction
- Booked
- 215 of 1,13219%
- Buildings
- 73.8 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 109
- 1 BHK
- 455
- 2 BHK
- 242
- 3 BHK
- 216
- 4 BHK
- 53
- 5+ BHK
- 6
- Other units
- 51
- Total units
- 1,132
- Buildings
- 7
- Land
- 3.8 acres
- Phases
- 1
- MahaRERA complaints
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 37% | 47% | 21% | 215 | |
| 37% | 47% | 21% | – | |
| 37% | 47% | 21% | – | |
| 37% | 47% | 21% | 215 |
"–" means MahaRERA shows no figure for that update.
About this project
Shreepati Jewels by Shreepati Jewels is a 1,132-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in July 2017 with possession due in December 2032. 215 units booked out of total 1,132 units. The concrete structure (RCC) is 47% complete.
Read full summary
Shreepati Jewels is a BMC-sanctioned project by Shreepati Jewels in Girgaon, Mumbai 400004, registered with MahaRERA as P51900001201. It was launched in July 2017. It has 1,132 units in 7 buildings: 1,081 homes (1 RK, 1 BHK, 2 BHK, 3 BHK, 4 BHK and 5+ BHK) and 51 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2032, extended by 8 years from the original December 2024. Construction: excavation 37% complete, structure (RCC) 47% complete, final finishes 21% complete.
215 units booked out of total 1,132 units (19%).
Shreepati's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 9 |
|---|---|
| Total units across these projects | 2,745 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 5 |
| Possession date extended on the builder's application | 3 |
| Typical time from launch to 100% structure | 7 years 5 months |
| MahaRERA complaints (filed by or against the builder), all Shreepati projects | 8 (3 of 9 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.