Shreepati projects in Mumbai
MahaRERA projects by Shreepati registered 2017–2025 in Mumbai.
| Projects registered with MahaRERA | 9 |
|---|---|
| Total units across these projects | 2,745 |
Full record
MahaRERA projects registered 2017–2025 in Mumbai
| Completed without extending the possession date | 1 |
|---|---|
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 5 |
| Possession date extended on the builder's application | 3 |
| Typical time from launch to 100% structure | 7 years 5 months |
| MahaRERA complaints (filed by or against the builder), all Shreepati projects | 8 (3 of 9 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Vile Parle West (2) · Girgaon (2) · Kalbadevi (1) · Mazgaon (1) · Dadar East (1) · Grant Road (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Aaradhya Avaan | Grant Road | Mid-construction | December 2030 | 176 units booked out of 279 units for sale |
| Jade Park · 2 phases | Vile Parle West | Early stage | Dec 2029 | – |
| Shreepati Coronet | Mazgaon | Mid-construction | December 2026 | 13 units booked out of total 29 units |
| Shreepati Jewels | Girgaon | Mid-construction | December 2032 | 215 units booked out of total 1,132 units |
Completed
| Project | Village | Status |
|---|---|---|
| Praman Splendour | Dadar East | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| Insignia | Vile Parle West | Lapsed |
| Shreepati Aradhana | Kalbadevi | Lapsed |
| Shreepati Castle | Girgaon | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.