Shreepati projects in Mumbai

MahaRERA projects by Shreepati registered 2017–2025 in Mumbai.

Projects registered with MahaRERA9
Total units across these projects2,745
Full record

MahaRERA projects registered 2017–2025 in Mumbai

Completed without extending the possession date1
Completed after an extension0
Lapsed3
Under construction5
Possession date extended on the builder's application3
Typical time from launch to 100% structure7 years 5 months
MahaRERA complaints (filed by or against the builder), all Shreepati projects8 (3 of 9 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Vile Parle West (2) · Girgaon (2) · Kalbadevi (1) · Mazgaon (1) · Dadar East (1) · Grant Road (1)

Under construction

ProjectVillageStagePossessionBooked
Aaradhya AvaanGrant RoadMid-constructionDecember 2030176 units booked out of 279 units for sale
Jade Park · 2 phasesVile Parle WestEarly stageDec 2029–
Shreepati CoronetMazgaonMid-constructionDecember 202613 units booked out of total 29 units
Shreepati JewelsGirgaonMid-constructionDecember 2032215 units booked out of total 1,132 units
Completed
ProjectVillageStatus
Praman SplendourDadar EastCompleted
Lapsed
ProjectVillageStatus
InsigniaVile Parle WestLapsed
Shreepati AradhanaKalbadeviLapsed
Shreepati CastleGirgaonLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.