Four Seasons Private Residences, Worli
Ready to moveLapsed
by Provenance Land Private Limited · Worli, Mumbai 400018 · Map
- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Dec 2024Extended in both phasesWhat does Lapsed mean?
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- –
- Buildings
- 21 acre
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 3
- 5+ BHK
- 5
- Other units
- 38
- Total units
- 46
- Buildings
- 2
- Land
- 1 acre
- Phases
- 2
- MahaRERA complaints
- 0
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Four Seasons Private Residences Phase - 1 Completed | P51900002789 | 6 | 100% | – | |
| Four Seasons Private Residences Phase - 2 Nearing possession Lapsed | P51900022056 | 2 | 100% | – |
Show updates by phase
Four Seasons Private Residences Phase - 1 (P51900002789)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | 24 |
"–" means MahaRERA shows no figure for that update.
Four Seasons Private Residences Phase - 2 (P51900022056)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 60% | – | |
| 100% | 100% | 60% | – | |
| 100% | 100% | 0% | 7 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Four Seasons Private Residences by Provenance Land Private Limited is a 46-unit project in Worli, Mumbai 400018, registered with MahaRERA in 2 phases, with possession due in December 2024. The concrete structure (RCC) is complete.
Read full summary
Four Seasons Private Residences is a project by Provenance Land Private Limited in Worli, Mumbai 400018, registered with MahaRERA as 2 phases (P51900002789, P51900022056). The first phase was launched in August 2017. Together the phases have 46 units in 2 buildings: 8 homes (2 and 5+ BHK) and 38 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is lapsed.
The registered possession date is December 2024; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 90% complete. Both phases have their structure complete.