Dilkap Victor, Andheri West
Lapsed
by Gorkap Properties & Investments Pvt Ltd · Andheri West, Mumbai 400053 · Map
- Launched
- Aug 20172 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2020Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 7 of 2825%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 28
- Total units
- 28
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 95% | 100% | 25% | 7 | |
| 95% | 100% | 25% | 7 | |
| 95% | 100% | 25% | 7 |
"–" means MahaRERA shows no figure for that update.
About this project
Dilkap Victor by Gorkap Properties & Investments Pvt Ltd is a 28-unit BMC-sanctioned project in Andheri West, Mumbai 400053, launched in August 2017; its MahaRERA registration has lapsed. 7 units booked out of total 28 units. The concrete structure (RCC) is complete.
Read full summary
Dilkap Victor is a BMC-sanctioned project by Gorkap Properties & Investments Pvt Ltd in Andheri West, Mumbai 400053, registered with MahaRERA as P51900002841. It was launched in August 2017. It has 28 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2020, after an extension of 1 year from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation 95% complete, structure (RCC) complete, final finishes 25% complete.
7 units booked out of total 28 units (25%).