Gulistan Manzil Co-operative Housing Society Limited, Santacruz East
Ready to moveLapsed
by Mishal Construction Private Limited · Santacruz East, Mumbai 400029 · Map
- Launched
- Aug 201710 mths originally promised
- Possession (MahaRERA)
- Jun 2019Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 19 of 2286%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 6
- 2 BHK
- 13
- Other units
- 3
- Total units
- 22
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 99% | 19 | |
| 100% | 100% | 99% | – | |
| 100% | 100% | 99% | – | |
| 100% | 100% | 99% | 19 |
"–" means MahaRERA shows no figure for that update.
About this project
Gulistan Manzil Co-operative Housing Society Limited by Mishal Construction Private Limited is a 22-unit project in Santacruz East, Mumbai 400029, launched in August 2017; its MahaRERA registration has lapsed. 19 units booked out of total 22 units. The concrete structure (RCC) is complete.
Read full summary
Gulistan Manzil Co-operative Housing Society Limited is a project by Mishal Construction Private Limited in Santacruz East, Mumbai 400029, registered with MahaRERA as P51900003234. It was launched in August 2017. It has 22 units in 1 building: 19 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2019, after an extension of 1 year from the original June 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 99% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
19 units booked out of total 22 units (86%).