Rustomjee Crown, Prabhadevi
Ready to move
by Realgem Buildtech Private Limited · Prabhadevi, Mumbai 400025 · Map
- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Dec 2024 – Oct 2027Extended in both phases
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- 279 of 34880%
- Buildings
- 33.6 acres
- MahaRERA complaints
- 96Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 251
- 4 BHK
- 97
- Total units
- 348
- Buildings
- 3
- Land
- 3.6 acres
- Phases
- 2
- MahaRERA complaints
- 96
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Rustomjee Crown - Phase I Ready to move Lapsed | P51900003268 | 0 | 100% | – | |
| Rustomjee Crown -Phase II Ready to move | P51900006367 | 348 | 100% | 80% |
Show updates by phase
Rustomjee Crown - Phase I (P51900003268)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | – | |
| 100% | 100% | 86% | 307 |
"–" means MahaRERA shows no figure for that update.
Rustomjee Crown -Phase II (P51900006367)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 92% | 279 | |
| 100% | 100% | 76% | 279 | |
| 100% | 89% | 15% | 0 | |
| 100% | 89% | 15% | 219 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Rustomjee Crown by Realgem Buildtech Private Limited (Rustomjee) is a 348-unit BMC-sanctioned project in Prabhadevi, Mumbai 400025, registered with MahaRERA in 2 phases, with possession dates from December 2024 to October 2027. 279 units booked out of total 348 units. The concrete structure (RCC) is complete.
Read full summary
Rustomjee Crown is a BMC-sanctioned project by Realgem Buildtech Private Limited in Prabhadevi, Mumbai 400025, registered with MahaRERA as 2 phases (P51900003268, P51900006367). The first phase was launched in August 2017. Together the phases have 348 units in 3 buildings, with 3 and 4 BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.
The phases' registered possession dates run from December 2024 to October 2027; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 92% complete. Both phases have their structure complete.
279 units booked out of total 348 units (80%).
Rustomjee's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 38 |
|---|---|
| Total units across these projects | 3,435 |
| Completed without extending the possession date | 15 |
| Completed after an extension | 2 |
| Lapsed | 5 |
| Under construction | 16 |
| Possession date extended on the builder's application | 8 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Rustomjee projects | 119 (11 of 38 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.