Rustomjee Crown, Prabhadevi

Ready to move

by Realgem Buildtech Private Limited · Prabhadevi, Mumbai 400025 · Map

Launched
Aug 2017First of 2 phases
Possession (MahaRERA)
Dec 2024 – Oct 2027Extended in both phases
Concrete structure
100%Weighted across 2 phases
Booked
279 of 34880%
Buildings
33.6 acres
MahaRERA complaints
96Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
251
4 BHK
97
Total units
348
Buildings
3
Land
3.6 acres
Phases
2
MahaRERA complaints
96

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Rustomjee Crown - Phase I
Ready to move Lapsed
P519000032680100%–
Rustomjee Crown -Phase II
Ready to move
P51900006367348100%80%
Show updates by phase

Rustomjee Crown - Phase I (P51900003268)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%86%307

"–" means MahaRERA shows no figure for that update.

Rustomjee Crown -Phase II (P51900006367)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%92%279
100%100%76%279
100%89%15%0
100%89%15%219

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services92%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 89%Dec 2025: Concrete structure (RCC) 89%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 15%Dec 2025: Final finishes 15%Jul 2026: Final finishes 76%Oct 2026: Final finishes 92%Excavation 100%Concrete structure (RCC) 100%Final finishes 92%

How to read construction stages

About this project

Rustomjee Crown by Realgem Buildtech Private Limited (Rustomjee) is a 348-unit BMC-sanctioned project in Prabhadevi, Mumbai 400025, registered with MahaRERA in 2 phases, with possession dates from December 2024 to October 2027. 279 units booked out of total 348 units. The concrete structure (RCC) is complete.

Read full summary

Rustomjee Crown is a BMC-sanctioned project by Realgem Buildtech Private Limited in Prabhadevi, Mumbai 400025, registered with MahaRERA as 2 phases (P51900003268, P51900006367). The first phase was launched in August 2017. Together the phases have 348 units in 3 buildings, with 3 and 4 BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.

The phases' registered possession dates run from December 2024 to October 2027; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 92% complete. Both phases have their structure complete.

279 units booked out of total 348 units (80%).

Rustomjee's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA38
Total units across these projects3,435
Completed without extending the possession date15
Completed after an extension2
Lapsed5
Under construction16
Possession date extended on the builder's application8
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Rustomjee projects119 (11 of 38 projects)

See all Rustomjee projects →