Piramal Aranya, Mazgaon

Ready to move

by Glider Buildcon Realtors Private Limited · Mazgaon, Mumbai 400010 · Map

Launched
Aug 2017First of 3 phases
Possession (MahaRERA)
Dec 2025 – Aug 2027Not extended
Concrete structure
100%Weighted across 3 phases
Booked
735 of 1,04670%
Buildings
30.3 acres
MahaRERA complaints
29Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
468
3 BHK
431
4 BHK
105
5+ BHK
42
Total units
1,046
Buildings
3
Land
0.3 acres
Phases
3
MahaRERA complaints
29

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Piramal Aranya - Wing A
Completed
P51900003324229100%65%
Piramal Aranya - Wing B
Ready to move Lapsed
P51900018039480100%69%
Piramal Aranya - Wing C
Ready to move
P51900020330337100%75%
Show updates by phase

Piramal Aranya - Wing A (P51900003324)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%148
100%100%100%148
100%100%100%163

"–" means MahaRERA shows no figure for that update.

Piramal Aranya - Wing B (P51900018039)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%333
100%100%100%333
100%100%100%295

"–" means MahaRERA shows no figure for that update.

Piramal Aranya - Wing C (P51900020330)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%254
100%100%95%254
100%100%50%243
100%100%50%186

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services98%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 84%Dec 2025: Final finishes 84%Jul 2026: Final finishes 98%Oct 2026: Final finishes 98%Excavation 100%Concrete structure (RCC) 100%Final finishes 98%

How to read construction stages

About this project

Piramal Aranya by Glider Buildcon Realtors Private Limited (Piramal) is a 1,046-unit BMC-sanctioned project in Mazgaon, Mumbai 400010, registered with MahaRERA in 3 phases, with possession dates from December 2025 to August 2027. 735 units booked out of total 1,046 units. The concrete structure (RCC) is complete.

Read full summary

Piramal Aranya is a BMC-sanctioned project by Glider Buildcon Realtors Private Limited in Mazgaon, Mumbai 400010, registered with MahaRERA as 3 phases (P51900003324, P51900018039, P51900020330). The first phase was launched in August 2017. Together the phases have 1,046 units in 3 buildings, with 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. On MahaRERA, 1 is completed, 1 is lapsed and 1 is active.

The phases' registered possession dates run from December 2025 to August 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 98% complete. All 3 phases have their structure complete.

735 units booked out of total 1,046 units (70%).

Piramal's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA13
Total units across these projects3,823
Completed without extending the possession date5
Completed after an extension0
Lapsed3
Under construction5
Possession date extended on the builder's application0
Typical time from launch to 100% structure6 years 2 months
MahaRERA complaints (filed by or against the builder), all Piramal projects83 (11 of 13 projects)