Piramal Aranya, Mazgaon
Ready to move
by Glider Buildcon Realtors Private Limited · Mazgaon, Mumbai 400010 · Map
- Launched
- Aug 2017First of 3 phases
- Possession (MahaRERA)
- Dec 2025 – Aug 2027Not extended
- Concrete structure
- 100%Weighted across 3 phases
- Booked
- 735 of 1,04670%
- Buildings
- 30.3 acres
- MahaRERA complaints
- 29Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 468
- 3 BHK
- 431
- 4 BHK
- 105
- 5+ BHK
- 42
- Total units
- 1,046
- Buildings
- 3
- Land
- 0.3 acres
- Phases
- 3
- MahaRERA complaints
- 29
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Piramal Aranya - Wing A Completed | P51900003324 | 229 | 100% | 65% | |
| Piramal Aranya - Wing B Ready to move Lapsed | P51900018039 | 480 | 100% | 69% | |
| Piramal Aranya - Wing C Ready to move | P51900020330 | 337 | 100% | 75% |
Show updates by phase
Piramal Aranya - Wing A (P51900003324)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 148 | |
| 100% | 100% | 100% | 148 | |
| 100% | 100% | 100% | 163 |
"–" means MahaRERA shows no figure for that update.
Piramal Aranya - Wing B (P51900018039)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 333 | |
| 100% | 100% | 100% | 333 | |
| 100% | 100% | 100% | 295 |
"–" means MahaRERA shows no figure for that update.
Piramal Aranya - Wing C (P51900020330)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 254 | |
| 100% | 100% | 95% | 254 | |
| 100% | 100% | 50% | 243 | |
| 100% | 100% | 50% | 186 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Piramal Aranya by Glider Buildcon Realtors Private Limited (Piramal) is a 1,046-unit BMC-sanctioned project in Mazgaon, Mumbai 400010, registered with MahaRERA in 3 phases, with possession dates from December 2025 to August 2027. 735 units booked out of total 1,046 units. The concrete structure (RCC) is complete.
Read full summary
Piramal Aranya is a BMC-sanctioned project by Glider Buildcon Realtors Private Limited in Mazgaon, Mumbai 400010, registered with MahaRERA as 3 phases (P51900003324, P51900018039, P51900020330). The first phase was launched in August 2017. Together the phases have 1,046 units in 3 buildings, with 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. On MahaRERA, 1 is completed, 1 is lapsed and 1 is active.
The phases' registered possession dates run from December 2025 to August 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 98% complete. All 3 phases have their structure complete.
735 units booked out of total 1,046 units (70%).
Piramal's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 13 |
|---|---|
| Total units across these projects | 3,823 |
| Completed without extending the possession date | 5 |
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 5 |
| Possession date extended on the builder's application | 0 |
| Typical time from launch to 100% structure | 6 years 2 months |
| MahaRERA complaints (filed by or against the builder), all Piramal projects | 83 (11 of 13 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.