Piramal projects in Mumbai

MahaRERA projects by Piramal registered 2017–2025 in Mumbai.

Projects registered with MahaRERA13
Total units across these projects3,823
Full record

MahaRERA projects registered 2017–2025 in Mumbai

Completed without extending the possession date5
Completed after an extension0
Lapsed3
Under construction5
Possession date extended on the builder's application0
Typical time from launch to 100% structure6 years 2 months
MahaRERA complaints (filed by or against the builder), all Piramal projects83 (11 of 13 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Mahalaxmi (3) · Mazgaon (2) · Mulund West (1)

Under construction

ProjectVillageStagePossessionBooked
North Tower - Tower 3MahalaxmiNearing possessionDecember 2026487 units booked out of total 496 units
Piramal Aranya · 3 phasesMazgaonReady to moveDec 2025 – Aug 2027735 units booked out of total 1,046 units
Piramal Aranya - Ahan 2MazgaonNearing possessionDecember 2027174 units booked out of total 292 units
Piramal Revanta · 6 phasesMulund WestMid-constructionNov 2028 – Jul 2030–
Lapsed
ProjectVillageStatus
CentralMahalaxmiLapsed
SouthMahalaxmiLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.