Piramal projects in Mumbai
MahaRERA projects by Piramal registered 2017–2025 in Mumbai.
| Projects registered with MahaRERA | 13 |
|---|---|
| Total units across these projects | 3,823 |
Full record
MahaRERA projects registered 2017–2025 in Mumbai
| Completed without extending the possession date | 5 |
|---|---|
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 5 |
| Possession date extended on the builder's application | 0 |
| Typical time from launch to 100% structure | 6 years 2 months |
| MahaRERA complaints (filed by or against the builder), all Piramal projects | 83 (11 of 13 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Mahalaxmi (3) · Mazgaon (2) · Mulund West (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| North Tower - Tower 3 | Mahalaxmi | Nearing possession | December 2026 | 487 units booked out of total 496 units |
| Piramal Aranya · 3 phases | Mazgaon | Ready to move | Dec 2025 – Aug 2027 | 735 units booked out of total 1,046 units |
| Piramal Aranya - Ahan 2 | Mazgaon | Nearing possession | December 2027 | 174 units booked out of total 292 units |
| Piramal Revanta · 6 phases | Mulund West | Mid-construction | Nov 2028 – Jul 2030 | – |
Lapsed
| Project | Village | Status |
|---|---|---|
| Central | Mahalaxmi | Lapsed |
| South | Mahalaxmi | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.