Aaditya Luxuria, Girgaon

by M/S. A.K. Developers · Girgaon, Mumbai 400004 · Map

Launched
Aug 20177 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 2 yrs
Concrete structure
90%Mid-construction
Booked
31 of 4865%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
13
3 BHK
23
4 BHK
9
5+ BHK
2
Total units
48
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 90%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%0%31
100%90%0%–
100%90%0%–
100%90%0%30

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400004

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400004
MeasureThis projectSimilar projects
Launch to possession (as first promised)7 yrs 4 mths5 yrs 8 mths
Possession date extendedBy 2 yrs5 of 6
Possession date (MahaRERA)Dec 2026Jul 2024
Concrete structure (RCC)90%100%
Units booked65%98%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Aaditya Luxuria by M/S. A.K. Developers is a 48-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in August 2017 with possession due in December 2026. 31 units booked out of total 48 units. The concrete structure (RCC) is 90% complete.

Read full summary

Aaditya Luxuria is a BMC-sanctioned project by M/S. A.K. Developers in Girgaon, Mumbai 400004, registered with MahaRERA as P51900003845. It was launched in August 2017. It has 48 units in 1 building, with 1, 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.

31 units booked out of total 48 units (65%).