- Launched
- Aug 20177 yrs 4 mths originally promised
- Possession (MahaRERA)
- Oct 2028Extended by 3 yrs 10 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 31 of 31100% · 51 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale31 booked out of 31 units
Rehab51 units for existing members
Total 82 units. Rehab units are not for sale.
Project facts
- 1 RK
- 3
- 1 BHK
- 17
- 2 BHK
- 34
- 3 BHK
- 9
- 4 BHK
- 2
- 5+ BHK
- 3
- Other units
- 14
- Total units
- 82
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 31
- Rehab units
- 51
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 96% | 31 | |
| 100% | 100% | 90% | 30 | |
| 100% | 100% | 87% | – | |
| 100% | 100% | 85% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400004
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 7 yrs 4 mths | 6 yrs 2 mths |
| Possession date extended | By 3 yrs 10 mths | 4 of 6 |
| Possession date (MahaRERA) | Oct 2028 | Sep 2026 |
| Concrete structure (RCC) | 100% | 95% |
| Units booked (free sale) | 100% | 65% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Lifescapes Arihant, Girgaon
- Aaditya Luxuria, Girgaon
- Aaditya Residences, Girgaon
- Nebula, Girgaon
- Krishvi Heights, Girgaon
- Dadamaharaj Heights, Girgaon
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Lifescapes Arihant | August 2017 | January 2025 | 100% | 60 units booked out of total 61 units |
| Aaditya Luxuria | August 2017 | December 2026 | 90% | 31 units booked out of total 48 units |
| Aaditya Residences | August 2017 | December 2026 | 0% | – |
| Nebula | August 2017 | June 2026 | 100% | 66 units booked out of total 122 units |
| Krishvi Heights | August 2017 | December 2022 | 100% | 27 units booked out of 31 units for sale |
| Dadamaharaj Heights | November 2017 | April 2027 | 83% | 56 units booked out of total 98 units |
About this project
Annapurna Sadan by D R Developers is an 82-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in August 2017 with possession due in October 2028. 31 units booked out of 31 units for sale. The concrete structure (RCC) is complete.
Read full summary
Annapurna Sadan is a BMC-sanctioned project by D R Developers in Girgaon, Mumbai 400004, registered with MahaRERA as P51900007411. It was launched in August 2017. It has 82 units in 1 building: 68 homes (1 RK, 1 BHK, 2 BHK, 3 BHK, 4 BHK and 5+ BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 82 units, 31 are for sale and 51 are rehab units for existing members.
Its registered possession date is October 2028, extended by 3 years 10 months from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes 96% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
31 units booked out of 31 units for sale (100%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from June 2026 to October 2028.