Empire Solitaire, Mahalaxmi

Lapsed

by Aalay Developers · Mahalaxmi, Mumbai 400011 · Map

Launched
Aug 20171 yr 4 mths originally promised
Possession (MahaRERA)
Dec 2024Extended by 6 yrsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
34 of 3694%
Buildings
10.2 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
7
2 BHK
27
3 BHK
2
Total units
36
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 75%Dec 2025: Final finishes 75%Jul 2026: Final finishes 75%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%34
100%100%75%–
100%100%75%–
100%100%75%34

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Empire Solitaire by Aalay Developers is a 36-unit project in Mahalaxmi, Mumbai 400011, launched in August 2017; its MahaRERA registration has lapsed. 34 units booked out of total 36 units. The concrete structure (RCC) is complete.

Read full summary

Empire Solitaire is a project by Aalay Developers in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900004114. It was launched in August 2017. It has 36 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024, after an extension of 6 years from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.

34 units booked out of total 36 units (94%).