Bombay Dyeing Mill, Dadar East

Lapsed

by Mhada · Dadar East, Mumbai 400014 · Map

Launched
Aug 20171 yr 4 mths originally promised
Possession (MahaRERA)
Dec 2023Extended by 5 yrsWhat does Lapsed mean?
Concrete structure
72%Mid-construction
Booked
–
Buildings
115.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
3,350
Total units
3,350
Buildings
11
Land
5.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)72%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 72%Dec 2025: Concrete structure (RCC) 72%Jul 2026: Concrete structure (RCC) 72%Oct 2026: Concrete structure (RCC) 72%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 72%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%72%0%–
100%72%0%–
100%72%0%–
100%72%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Bombay Dyeing Mill by Mhada is a 3,350-unit project in Dadar East, Mumbai 400014, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 72% complete.

Read full summary

Bombay Dyeing Mill is a project by Mhada in Dadar East, Mumbai 400014, registered with MahaRERA as P51900004280. It was launched in August 2017. It has 3,350 units in 11 buildings, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023, after an extension of 5 years from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 72% complete, final finishes not started.