Kohinoor Square, Dadar West
Lapsed
by Kohinoor CTNL Infrastructure Company Private Limited · Dadar West, Mumbai 400028 · Map
- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Sep 2023Extended in 1 of 2 phasesWhat does Lapsed mean?
- Concrete structure
- 99%Weighted across 2 phases
- Booked
- –
- Buildings
- 32.9 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 320
- Total units
- 320
- Buildings
- 3
- Land
- 2.9 acres
- Phases
- 2
- MahaRERA complaints
- 3
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Kohinoor Square Phase 1 Mid-construction Lapsed | P51900004769 | 0 | 98% | 100% | |
| Kohinoor Square Phase 2 Completed | P51900012308 | 0 | 100% | – |
Show updates by phase
Kohinoor Square Phase 1 (P51900004769)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 98% | 99% | 199 | |
| 100% | 98% | 99% | 199 | |
| 100% | 100% | 100% | 202 |
"–" means MahaRERA shows no figure for that update.
Kohinoor Square Phase 2 (P51900012308)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | 121 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Kohinoor Square by Kohinoor CTNL Infrastructure Company Private Limited is a 320-unit project in Dadar West, Mumbai 400028, registered with MahaRERA in 2 phases, with possession due in September 2023. The concrete structure (RCC) is 99% complete.
Read full summary
Kohinoor Square is a project by Kohinoor CTNL Infrastructure Company Private Limited in Dadar West, Mumbai 400028, registered with MahaRERA as 2 phases (P51900004769, P51900012308). The first phase was launched in August 2017. Together the phases have 320 units in 3 buildings, as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is completed.
The registered possession date is September 2023; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 99% complete and final finishes 99% complete. Neither phase has its structure complete.