Godrej Avenue Eleven, Mumbai Central
by Godrej Residency Private Limited · Mumbai Central, Mumbai 400008 · Map
- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Dec 2028 – Apr 2030Extended in both phases
- Concrete structure
- 56%Weighted across 2 phases
- Booked
- 359 of 40888% · 318 in Jul 2026
- Buildings
- 22.1 acres
- MahaRERA complaints
- 15Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 47
- 4 BHK
- 361
- Total units
- 408
- Buildings
- 2
- Land
- 2.1 acres
- Phases
- 2
- MahaRERA complaints
- 15
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Godrej Avenue Eleven - Tower A Mid-construction | P51900005216 | 227 | 99% | 89% | |
| Godrej Avenue Eleven - Tower B Mid-construction | P51900006299 | 181 | 2% | 87% |
Show updates by phase
Godrej Avenue Eleven - Tower A (P51900005216)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 99% | 0% | 201 | |
| 100% | 87% | 0% | 164 | |
| 100% | 58% | 0% | 160 | |
| 100% | 50% | 0% | 156 |
"–" means MahaRERA shows no figure for that update.
Godrej Avenue Eleven - Tower B (P51900006299)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 2% | 0% | 158 | |
| 100% | 0% | 0% | 154 | |
| 100% | 0% | 0% | 145 | |
| 18% | 0% | 0% | 72 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Godrej Avenue Eleven by Godrej Residency Private Limited is a 408-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, registered with MahaRERA in 2 phases, with possession dates from December 2028 to April 2030. 359 units booked out of total 408 units. The concrete structure (RCC) is 56% complete.
Read full summary
Godrej Avenue Eleven is a BMC-sanctioned project by Godrej Residency Private Limited in Mumbai Central, Mumbai 400008, registered with MahaRERA as 2 phases (P51900005216, P51900006299). The first phase was launched in August 2017. Together the phases have 408 units in 2 buildings, with 3 and 4 BHK homes as registered with MahaRERA. Both phases are active on MahaRERA.
The phases' registered possession dates run from December 2028 to April 2030; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 56% complete and final finishes 0% complete. Neither phase has its structure complete.
359 units booked out of total 408 units (88%). Since the July 2026 update, 41 more units have been booked.
Godrej's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 35 |
|---|---|
| Total units across these projects | 10,289 |
| Completed without extending the possession date | 9 |
| Completed after an extension | 0 |
| Lapsed | 2 |
| Under construction | 24 |
| Possession date extended on the builder's application | 5 |
| Typical time from launch to 100% structure | 6 years 3 months |
| MahaRERA complaints (filed by or against the builder), all Godrej projects | 86 (17 of 35 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.