Cornerstone, Worli

Lapsed

by Shree Sadguru & Deluxe JV · Worli, Mumbai 400018 · Map

Launched
Aug 20176 yrs 10 mths originally promised
Possession (MahaRERA)
Jun 2025Extended by 1 yrWhat does Lapsed mean?
Concrete structure
98%Mid-construction
Booked
–
Buildings
10.4 acres
MahaRERA complaints
6Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)98%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 97%Dec 2025: Concrete structure (RCC) 98%Jul 2026: Concrete structure (RCC) 98%Dec 2024: Final finishes 50%Dec 2025: Final finishes 60%Jul 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 98%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%98%60%–
100%98%60%–
100%97%50%137

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Cornerstone by Shree Sadguru & Deluxe JV is a project in Worli, Mumbai 400018, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 98% complete.

Read full summary

Cornerstone is a project by Shree Sadguru & Deluxe JV in Worli, Mumbai 400018, registered with MahaRERA as P51900005370. It was launched in August 2017. Its MahaRERA status is Lapsed.

Possession was due in June 2025, after an extension of 1 year from the original June 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 98% complete, final finishes 60% complete.