Chistiya Palace, Mahalaxmi
Ready to moveLapsed
by Rensar Infra PvtLtd · Mahalaxmi, Mumbai 400011 · Map
- Launched
- Aug 20174 yrs 11 mths originally promised
- Possession (MahaRERA)
- Oct 2026Extended by 4 yrs 3 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 14 of 1688%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 8
- 3 BHK
- 4
- 4 BHK
- 4
- Total units
- 16
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 14 | |
| 100% | 100% | 95% | 14 | |
| 100% | 100% | 95% | 14 | |
| 100% | 100% | 95% | 14 |
"–" means MahaRERA shows no figure for that update.
About this project
Chistiya Palace by Rensar Infra PvtLtd is a 16-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in August 2017; its MahaRERA registration has lapsed. 14 units booked out of total 16 units. The concrete structure (RCC) is complete.
Read full summary
Chistiya Palace is a BMC-sanctioned project by Rensar Infra PvtLtd in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900005473. It was launched in August 2017. It has 16 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Its registered possession date is October 2026, extended by 4 years 3 months from the original July 2022. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
14 units booked out of total 16 units (88%).