Chistiya Palace, Mahalaxmi

Ready to moveLapsed

by Rensar Infra PvtLtd · Mahalaxmi, Mumbai 400011 · Map

Launched
Aug 20174 yrs 11 mths originally promised
Possession (MahaRERA)
Oct 2026Extended by 4 yrs 3 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
14 of 1688%
Buildings
10.2 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
8
3 BHK
4
4 BHK
4
Total units
16
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 95%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%14
100%100%95%14
100%100%95%14
100%100%95%14

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Chistiya Palace by Rensar Infra PvtLtd is a 16-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in August 2017; its MahaRERA registration has lapsed. 14 units booked out of total 16 units. The concrete structure (RCC) is complete.

Read full summary

Chistiya Palace is a BMC-sanctioned project by Rensar Infra PvtLtd in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900005473. It was launched in August 2017. It has 16 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Its registered possession date is October 2026, extended by 4 years 3 months from the original July 2022. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

14 units booked out of total 16 units (88%).