Runwal Timeless, Sion
by Runwal Developers Limited · Sion, Mumbai 400022 · Map
- Launched
- Aug 20179 yrs 1 mth originally promised
- Possession (MahaRERA)
- Jan 2029Extended by 2 yrs 4 mths
- Concrete structure
- 70%Mid-construction
- Booked
- 540 of 74972% · 527 in Jul 2026
- Buildings
- 13 acres
- MahaRERA complaints
- 10Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 76
- 2 BHK
- 524
- 3 BHK
- 147
- 4 BHK
- 2
- Total units
- 749
- Buildings
- 1
- Land
- 3 acres
- Phases
- 1
- MahaRERA complaints
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 10% | 540 | |
| 100% | 4% | 0% | 527 | |
| 100% | 4% | 0% | 441 | |
| 100% | 0% | 0% | 435 |
"–" means MahaRERA shows no figure for that update.
About this project
Runwal Timeless by Runwal Developers Limited is a 749-unit SRA-sanctioned project in Sion, Mumbai 400022, launched in August 2017 with possession due in January 2029. 540 units booked out of total 749 units. The concrete structure (RCC) is 70% complete.
Read full summary
Runwal Timeless is an SRA-sanctioned project by Runwal Developers Limited in Sion, Mumbai 400022, registered with MahaRERA as P51900005685. It was launched in August 2017. It has 749 units in 1 building, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is January 2029, extended by 2 years 4 months from the original September 2026. Construction: excavation complete, structure (RCC) 70% complete, final finishes 10% complete.
540 units booked out of total 749 units (72%). Since the July 2026 update, 13 more units have been booked, the reported concrete structure (RCC) has gone from 4% to 70% and the possession date has moved from September 2026 to January 2029.
Runwal's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 46 |
|---|---|
| Total units across these projects | 14,623 |
| Completed without extending the possession date | 10 |
| Completed after an extension | 5 |
| Lapsed | 5 |
| Under construction | 26 |
| Possession date extended on the builder's application | 16 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Runwal projects | 343 (35 of 46 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.