Tejaswini Heights, Parel

Lapsed

by Tejaswini Homes PvtLtd · Parel, Mumbai 400012 · Map

Launched
Aug 20174 yrs 4 mths promised
Possession (MahaRERA)
Dec 2021Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
24 of 3275%
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
32
Total units
32
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%24
100%0%0%–
100%0%0%–
100%0%0%24

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Tejaswini Heights by Tejaswini Homes PvtLtd is a 32-unit project in Parel, Mumbai 400012, launched in August 2017; its MahaRERA registration has lapsed. 24 units booked out of total 32 units. Work on the concrete structure (RCC) has not started.

Read full summary

Tejaswini Heights is a project by Tejaswini Homes PvtLtd in Parel, Mumbai 400012, registered with MahaRERA as P51900005855. It was launched in August 2017. It has 32 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2021. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.

24 units booked out of total 32 units (75%).