Palais Royale, Lower Parel

Lapsed

by Honest Shelters Private Ltd · Lower Parel, Mumbai 400013 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2024Extended by 2 yrsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
77 of 16248%
Buildings
17 acres
MahaRERA complaints
56Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
162
Total units
162
Buildings
1
Land
7 acres
Phases
1
MahaRERA complaints
56

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services65%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 65%Dec 2025: Final finishes 65%Jul 2026: Final finishes 65%Oct 2026: Final finishes 65%Excavation 100%Concrete structure (RCC) 100%Final finishes 65%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%65%77
100%100%65%–
100%100%65%–
100%100%65%77

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Palais Royale by Honest Shelters Private Ltd is a 162-unit BMC-sanctioned project in Lower Parel, Mumbai 400013, launched in August 2017; its MahaRERA registration has lapsed. 77 units booked out of total 162 units. The concrete structure (RCC) is complete.

Read full summary

Palais Royale is a BMC-sanctioned project by Honest Shelters Private Ltd in Lower Parel, Mumbai 400013, registered with MahaRERA as P51900006786. It was launched in August 2017. It has 162 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024, after an extension of 2 years from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 65% complete.

77 units booked out of total 162 units (48%).