Prince Tower, Dharavi
Ready to moveLapsed
by Punith Buildtech Private Limited · Dharavi, Mumbai 400017 · Map
- Launched
- Aug 20175 yrs 4 mths originally promised
- Possession (MahaRERA)
- Jun 2025Extended by 2 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 77 of 10176%
- Buildings
- 10.6 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 2 BHK
- 100
- Total units
- 101
- Buildings
- 1
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 98% | 77 | |
| 100% | 100% | 98% | 77 | |
| 100% | 100% | 98% | 77 | |
| 100% | 100% | 30% | 23 |
"–" means MahaRERA shows no figure for that update.
About this project
Prince Tower by Punith Buildtech Private Limited is a 101-unit SRA-sanctioned project in Dharavi, Mumbai 400017, launched in August 2017; its MahaRERA registration has lapsed. 77 units booked out of total 101 units. The concrete structure (RCC) is complete.
Read full summary
Prince Tower is an SRA-sanctioned project by Punith Buildtech Private Limited in Dharavi, Mumbai 400017, registered with MahaRERA as P51900006933. It was launched in August 2017. It has 101 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2025, after an extension of 2 years 6 months from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
77 units booked out of total 101 units (76%).