Construction of Mill Workers Tenements at Shrinivas MIll Lower Parel, Lower Parel
Ready to moveLapsed
by Mhada · Lower Parel, Mumbai 400013 · Map
- Launched
- Aug 20171 yr 4 mths originally promised
- Possession (MahaRERA)
- Dec 2023Extended by 5 yrsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- –
- Buildings
- 11.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 544
- Total units
- 544
- Buildings
- 1
- Land
- 1.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Construction of Mill Workers Tenements at Shrinivas MIll Lower Parel by Mhada is a 544-unit project in Lower Parel, Mumbai 400013, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.
Read full summary
Construction of Mill Workers Tenements at Shrinivas MIll Lower Parel is a project by Mhada in Lower Parel, Mumbai 400013, registered with MahaRERA as P51900007421. It was launched in August 2017. It has 544 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2023, after an extension of 5 years from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.