Cosmos Platinum Business Park, Dadar West

Ready to moveLapsed

by J R Properties · Dadar West, Mumbai 400028 · Map

Launched
Aug 20172 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2020Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
–
Buildings
10.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
68
Total units
68
Buildings
1
Land
0.7 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services98%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 98%Dec 2025: Final finishes 98%Jul 2026: Final finishes 98%Excavation 100%Concrete structure (RCC) 100%Final finishes 98%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%98%–
100%100%98%–
100%100%98%38

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Cosmos Platinum Business Park by J R Properties is a 68-unit project in Dadar West, Mumbai 400028, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Cosmos Platinum Business Park is a project by J R Properties in Dadar West, Mumbai 400028, registered with MahaRERA as P51900007433. It was launched in August 2017. It has 68 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2020, after an extension of 1 year from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.