- Launched
- Aug 20177 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2024Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- –
- Buildings
- 10.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 101
- 2 BHK
- 21
- 3 BHK
- 23
- 4 BHK
- 3
- Other units
- 24
- Total units
- 172
- Buildings
- 1
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 5% | – | |
| 100% | 100% | 5% | – | |
| 100% | 100% | 5% | 148 |
"–" means MahaRERA shows no figure for that update.
About this project
Aaditya Heights by Sanghvi Realty Pivate Ltd is a 172-unit project in Tardeo, Mumbai 400034, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.
Read full summary
Aaditya Heights is a project by Sanghvi Realty Pivate Ltd in Tardeo, Mumbai 400034, registered with MahaRERA as P51900007497. It was launched in August 2017. It has 172 units in 1 building: 148 homes (1, 2, 3 and 4 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 5% complete.