Skip to main content

Aaditya Heights, Tardeo

Lapsed

by Sanghvi Realty Pivate Ltd · Tardeo, Mumbai 400034 · Map

Launched
Aug 20177 yrs 4 mths promised
Possession (MahaRERA)
Dec 2024Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.9 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
101
2 BHK
21
3 BHK
23
4 BHK
3
Other units
24
Total units
172
Buildings
1
Land
0.9 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services5%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 5%Dec 2025: Final finishes 5%Jul 2026: Final finishes 5%Excavation 100%Concrete structure (RCC) 100%Final finishes 5%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%5%–
100%100%5%–
100%100%5%148

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Aaditya Heights by Sanghvi Realty Pivate Ltd is a 172-unit project in Tardeo, Mumbai 400034, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Aaditya Heights is a project by Sanghvi Realty Pivate Ltd in Tardeo, Mumbai 400034, registered with MahaRERA as P51900007497. It was launched in August 2017. It has 172 units in 1 building: 148 homes (1, 2, 3 and 4 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 5% complete.