Skip to main content

Crescent Tower, Kemps Corner

Lapsed

by Crescent Builders · Kemps Corner, Mumbai 400036 · Map

Launched
Aug 20171 yr 7 mths promised
Possession (MahaRERA)
Mar 2019Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
35 of 4088%
Buildings
12.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
7
3 BHK
30
4 BHK
3
Total units
40
Buildings
1
Land
2.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services78%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 78%Dec 2025: Final finishes 78%Jul 2026: Final finishes 78%Oct 2026: Final finishes 78%Excavation 100%Concrete structure (RCC) 100%Final finishes 78%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%78%35
100%100%78%–
100%100%78%–
100%100%78%35

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Crescent Tower by Crescent Builders is a 40-unit project in Kemps Corner, Mumbai 400036, launched in August 2017; its MahaRERA registration has lapsed. 35 units booked out of total 40 units. The concrete structure (RCC) is complete.

Read full summary

Crescent Tower is a project by Crescent Builders in Kemps Corner, Mumbai 400036, registered with MahaRERA as P51900007712. It was launched in August 2017. It has 40 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in March 2019. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 78% complete.

35 units booked out of total 40 units (88%).