Palette, Dadar West

by Suraj Estate Developers Ltd · Dadar West, Mumbai 400028 · Map

Launched
Aug 20175 yrs 10 mths originally promised
Possession (MahaRERA)
Jan 2027Extended by 3 yrs 7 mths
Concrete structure
97%Mid-construction
Booked (free sale)
129 of 14589% · 7 rehab units
Buildings
10.8 acres
MahaRERA complaints
6Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale129 booked out of 145 units

Rehab7 units for existing members

Total 152 units. Rehab units are not for sale.

Project facts

1 RK
1
2 BHK
40
3 BHK
111
Total units
152
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
6
Free-sale units
145
Rehab units
7

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)97%
Finishes, lifts and services25%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 97%Jul 2026: Concrete structure (RCC) 97%Oct 2026: Concrete structure (RCC) 97%Dec 2024: Final finishes 0%Dec 2025: Final finishes 25%Jul 2026: Final finishes 25%Oct 2026: Final finishes 25%Excavation 100%Concrete structure (RCC) 97%Final finishes 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%97%25%129
100%97%25%128
100%97%25%132
100%90%0%120

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Palette by Suraj Estate Developers Ltd is a 152-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in August 2017 with possession due in January 2027. 129 units booked out of 145 units for sale. The concrete structure (RCC) is 97% complete.

Read full summary

Palette is a BMC-sanctioned project by Suraj Estate Developers Ltd in Dadar West, Mumbai 400028, registered with MahaRERA as P51900008207. It was launched in August 2017. It has 152 units in 1 building, with 1 RK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 152 units, 145 are for sale and 7 are rehab units for existing members.

Its registered possession date is January 2027, extended by 3 years 7 months from the original June 2023. Construction: excavation complete, structure (RCC) 97% complete, final finishes 25% complete.

129 units booked out of 145 units for sale (89%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from June 2024 to January 2027.

Suraj Estate's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA17
Total units across these projects1,217
Completed without extending the possession date0
Completed after an extension4
Lapsed3
Under construction10
Possession date extended on the builder's application10
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Suraj Estate projects11 (6 of 17 projects)