Palette, Dadar West
by Suraj Estate Developers Ltd · Dadar West, Mumbai 400028 · Map
- Launched
- Aug 20175 yrs 10 mths originally promised
- Possession (MahaRERA)
- Jan 2027Extended by 3 yrs 7 mths
- Concrete structure
- 97%Mid-construction
- Booked (free sale)
- 129 of 14589% · 7 rehab units
- Buildings
- 10.8 acres
- MahaRERA complaints
- 6Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale129 booked out of 145 units
Rehab7 units for existing members
Total 152 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 2 BHK
- 40
- 3 BHK
- 111
- Total units
- 152
- Buildings
- 1
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 6
- Free-sale units
- 145
- Rehab units
- 7
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 97% | 25% | 129 | |
| 100% | 97% | 25% | 128 | |
| 100% | 97% | 25% | 132 | |
| 100% | 90% | 0% | 120 |
"–" means MahaRERA shows no figure for that update.
About this project
Palette by Suraj Estate Developers Ltd is a 152-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in August 2017 with possession due in January 2027. 129 units booked out of 145 units for sale. The concrete structure (RCC) is 97% complete.
Read full summary
Palette is a BMC-sanctioned project by Suraj Estate Developers Ltd in Dadar West, Mumbai 400028, registered with MahaRERA as P51900008207. It was launched in August 2017. It has 152 units in 1 building, with 1 RK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 152 units, 145 are for sale and 7 are rehab units for existing members.
Its registered possession date is January 2027, extended by 3 years 7 months from the original June 2023. Construction: excavation complete, structure (RCC) 97% complete, final finishes 25% complete.
129 units booked out of 145 units for sale (89%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from June 2024 to January 2027.
Suraj Estate's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 17 |
|---|---|
| Total units across these projects | 1,217 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 4 |
| Lapsed | 3 |
| Under construction | 10 |
| Possession date extended on the builder's application | 10 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Suraj Estate projects | 11 (6 of 17 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.