Pearl Residency, Dharavi

Lapsed

by Pushpa Construction Co · Dharavi, Mumbai 400017 · Map

Launched
Aug 20173 yrs 2 mths originally promised
Possession (MahaRERA)
Apr 2023Extended by 2 yrs 6 mthsWhat does Lapsed mean?
Concrete structure
51%Mid-construction
Booked
–
Buildings
22.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
31
2 BHK
152
3 BHK
48
Other units
13
Total units
244
Buildings
2
Land
2.8 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation95%
Concrete structure (slabs)51%
Finishes, lifts and services3%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 95%Dec 2025: Excavation 95%Jul 2026: Excavation 95%Dec 2024: Concrete structure (RCC) 51%Dec 2025: Concrete structure (RCC) 51%Jul 2026: Concrete structure (RCC) 51%Dec 2024: Final finishes 3%Dec 2025: Final finishes 3%Jul 2026: Final finishes 3%Excavation 95%Concrete structure (RCC) 51%Final finishes 3%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%51%3%–
95%51%3%–
95%51%3%48

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Pearl Residency by Pushpa Construction Co is a 244-unit project in Dharavi, Mumbai 400017, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 51% complete.

Read full summary

Pearl Residency is a project by Pushpa Construction Co in Dharavi, Mumbai 400017, registered with MahaRERA as P51900008616. It was launched in August 2017. It has 244 units in 2 buildings: 231 homes (1, 2 and 3 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in April 2023, after an extension of 2 years 6 months from the original October 2020. That date has passed and no further extension has been recorded. Construction: excavation 95% complete, structure (RCC) 51% complete, final finishes 3% complete.