- Launched
- Aug 20173 yrs 2 mths originally promised
- Possession (MahaRERA)
- Apr 2023Extended by 2 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 51%Mid-construction
- Booked
- –
- Buildings
- 22.8 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 31
- 2 BHK
- 152
- 3 BHK
- 48
- Other units
- 13
- Total units
- 244
- Buildings
- 2
- Land
- 2.8 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 95% | 51% | 3% | – | |
| 95% | 51% | 3% | – | |
| 95% | 51% | 3% | 48 |
"–" means MahaRERA shows no figure for that update.
About this project
Pearl Residency by Pushpa Construction Co is a 244-unit project in Dharavi, Mumbai 400017, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 51% complete.
Read full summary
Pearl Residency is a project by Pushpa Construction Co in Dharavi, Mumbai 400017, registered with MahaRERA as P51900008616. It was launched in August 2017. It has 244 units in 2 buildings: 231 homes (1, 2 and 3 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in April 2023, after an extension of 2 years 6 months from the original October 2020. That date has passed and no further extension has been recorded. Construction: excavation 95% complete, structure (RCC) 51% complete, final finishes 3% complete.