Skip to main content

Beaumonte Tower A, Sion

Ready to moveLapsed

by Sahana-Sheth · Sion, Mumbai 400022 · Map

Launched
Aug 20176 yrs 4 mths promised
Possession (MahaRERA)
Dec 2023Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
–
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
29
3 BHK
29
4 BHK
53
Total units
111
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 90%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%–
100%100%90%–
100%100%90%111

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Beaumonte Tower A by Sahana-Sheth is a 111-unit project in Sion, Mumbai 400022, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Beaumonte Tower A is a project by Sahana-Sheth in Sion, Mumbai 400022, registered with MahaRERA as P51900008720. It was launched in August 2017. It has 111 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.