Hubtown - Celeste, Worli
by Nayan Real Estate Private Limited · Worli, Mumbai 400018 · Map
- Launched
- Aug 201711 yrs 11 mths promised
- Possession (MahaRERA)
- Jul 2029Not extended
- Concrete structure
- 92%Mid-construction
- Booked
- 49 of 19126% · 35 in Jul 2026
- Buildings
- 10.1 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 191
- Total units
- 191
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 92% | 1% | 49 | |
| 100% | 81% | 1% | 35 | |
| 100% | 53% | 1% | – | |
| 100% | 53% | 1% | 41 |
"–" means MahaRERA shows no figure for that update.
About this project
Hubtown - Celeste by Nayan Real Estate Private Limited (Hubtown) is a 191-unit SRA-sanctioned project in Worli, Mumbai 400018, launched in August 2017 with possession due in July 2029. 49 units booked out of total 191 units. The concrete structure (RCC) is 92% complete.
Read full summary
Hubtown - Celeste is an SRA-sanctioned project by Nayan Real Estate Private Limited in Worli, Mumbai 400018, registered with MahaRERA as P51900008925. It was launched in August 2017. It has 191 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is July 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 92% complete, final finishes 1% complete.
49 units booked out of total 191 units (26%). Since the July 2026 update, 14 more units have been booked and the reported concrete structure (RCC) has gone from 81% to 92%.
Hubtown's track record in Mumbai
MahaRERA projects registered 2017–2023 in Mumbai
| Projects registered with MahaRERA | 27 |
|---|---|
| Total units across these projects | 1,419 |
| Completed without extending the possession date | 11 |
| Completed after an extension | 0 |
| Lapsed | 10 |
| Under construction | 6 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Hubtown projects | 234 (14 of 27 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.