Raghvendra CHS, Santacruz East

Lapsed

by Vinayak Developers And Builders · Santacruz East, Mumbai 400055 · Map

Launched
Aug 20171 yr 11 mths originally promised
Possession (MahaRERA)
Mar 2020Extended by 8 mthsWhat does Lapsed mean?
Concrete structure
50%Mid-construction
Booked
–
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
9
Total units
9
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)50%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 50%Oct 2026: Concrete structure (RCC) 50%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 50%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%0%–
100%50%0%–
100%50%0%–
100%50%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Raghvendra CHS by Vinayak Developers And Builders is a 9-unit project in Santacruz East, Mumbai 400055, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 50% complete.

Read full summary

Raghvendra CHS is a project by Vinayak Developers And Builders in Santacruz East, Mumbai 400055, registered with MahaRERA as P51900009068. It was launched in August 2017. It has 9 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in March 2020, after an extension of 8 months from the original July 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.