Terrain Heights, Santacruz East

Lapsed

by Terrain Infrastructure Pvt Ltd · Santacruz East, Mumbai 400055 · Map

Launched
Aug 20171 yr 7 mths originally promised
Possession (MahaRERA)
Mar 2020Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.4 acres
MahaRERA complaints
12Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
43
Total units
43
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services45%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 45%Dec 2025: Final finishes 45%Jul 2026: Final finishes 45%Excavation 100%Concrete structure (RCC) 100%Final finishes 45%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%45%–
100%100%45%–
100%100%45%43

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Terrain Heights by Terrain Infrastructure Pvt Ltd is a 43-unit project in Santacruz East, Mumbai 400055, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Terrain Heights is a project by Terrain Infrastructure Pvt Ltd in Santacruz East, Mumbai 400055, registered with MahaRERA as P51900009101. It was launched in August 2017. It has 43 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in March 2020, after an extension of 1 year from the original March 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 45% complete.