The Autograph, Wadala West

Lapsed

by Ozone Homes Pvt Ltd · Wadala West, Mumbai 400031 · Map

Launched
Aug 20176 yrs 4 mths promised
Possession (MahaRERA)
Dec 2023Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
43 of 11836%
Buildings
10.5 acres
MahaRERA complaints
22Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
66
3 BHK
50
Other units
2
Total units
118
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
22

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%43
0%0%0%–
0%0%0%–
0%0%0%43

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

The Autograph by Ozone Homes Pvt Ltd is a 118-unit project in Wadala West, Mumbai 400031, launched in August 2017; its MahaRERA registration has lapsed. 43 units booked out of total 118 units. Work on the concrete structure (RCC) has not started.

Read full summary

The Autograph is a project by Ozone Homes Pvt Ltd in Wadala West, Mumbai 400031, registered with MahaRERA as P51900009133. It was launched in August 2017. It has 118 units in 1 building: 116 homes (2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023. That date has passed and no extension has been recorded. Construction: excavation not started, structure (RCC) not started, final finishes not started.

43 units booked out of total 118 units (36%).